Metro Line 6: TBM Sfânta Maria reaches Expoziției

The tunnel boring machine (TBM) “Sfânta Maria” has reached the future Expoziției metro station, a key component of Metro Line 6 connecting to Otopeni Airport. The equipment has thus completed the fourth tunnel segment on Line 2 of the South Section, part of the underground route planned between the future Tokyo station and 1 Mai station.

As of October 8, 2026, TBM “Sfânta Maria” excavated 3.67 km out of a total 6.6 km of tunnel toward 1 Mai station and installed 2,445 structural rings, having been commissioned on April 9. Concurrently, as of October 8, 2026, the second machine, TBM “Sfânta Ana”, had 855 meters remaining to reach Expoziției station within the design and construction works for the structural frameworks of the stations, galleries, and tunnels in the South Section. For Section 1.2, which connects Tokyo station to Otopeni Airport, Metrorex signed a construction contract in May 2023 for structural frameworks with the joint venture Gülermak Ağir Sanayi Inșaat Ve Taahhüt A.S. – Somet SA. Gülermak is also involved, alongside Alstom and Arcada, in the construction of the Cluj-Napoca metro. Section 1.2 has a length of 7.6 km and will include six stations—Washington, Paris, Bruxelles, Otopeni, Ion I.C. Brătianu, and Aeroport Otopeni—completing, upon final delivery, the direct connection between 1 Mai station and the airport.

Frequently Asked Questions

What milestone did TBM Sfânta Maria reach on Metro Line 6?

The tunnel boring machine reached the future Expoziției station, completing the fourth tunnel segment on Line 2 of the South Section.

How much tunnel has TBM Sfânta Maria excavated?

It excavated 3.67 km out of a total 6.6 km toward 1 Mai station and installed 2,445 structural rings.

Which stations are included in Section 1.2 toward Otopeni Airport?

Section 1.2 spans 7.6 km and includes six stations: Washington, Paris, Bruxelles, Otopeni, Ion I.C. Brătianu, and Aeroport Otopeni.