Major progress on the Transylvania Motorway

Infrastructure works on the Transylvania Motorway (A3) have entered a decisive stage with the start of laying the first asphalt layer on the 2-kilometer viaduct at Mihăiești, located on the section between Nădășelu and Zimbor. The project, which provides a fast road connection between Cluj and Zalău, is progressing steadily, with authorities aiming to open traffic on the entire section by the end of 2026, enabling an uninterrupted 155-kilometer motorway route between Poarta Sălajului and Târgu Mureș.

On the 30-kilometer section between Nădășelu and Zimbor, physical progress on the 25 kilometers contracted to builder UMB has surpassed 99%, while the second contract, which includes the Nădășelu and Mihăiești viaducts, has exceeded 85%. At the Mihăiești viaduct, contractor Ozaltin has completed pouring the concrete deck slab and installing the guardrail, commencing asphalt paving, while at the Nădășelu viaduct, the cantilever section over the cemetery has been finalized. UMB is carrying out final works on service areas, overpasses, and protective fencing. As of October 13, 2026, 356 workers and 239 pieces of equipment from the Ozaltin–Ilgaz–Visio Construct joint venture were deployed on-site, with the contract value standing at EUR 186.43 million excluding VAT, funded via the Transport Programme 2021-2027. In August 2026, traffic was opened on the Zimbor–Poarta Sălajului section, whose length is officially reported at 12 or 12.24 kilometers, with access via the Zimbor and Românași junctions. Additionally, the total length of the Nădășelu–Poarta Sălajului section shows a slight discrepancy in reports, recorded as either 42.78 kilometers or 42.84 kilometers. This major project encompasses two interchanges, 14 bridges and overpasses, and 18 viaducts, with a total value exceeding EUR 861.91 million, of which EUR 239.84 million is financed through the NRRP (PNRR). During a site inspection at Nădășelu, Topa Mică, Poarta Sălajului, and Românași, Prime Minister Ilie Bolojan stated that, starting December 1, 2026, traffic would run unrestricted across more than 40 new kilometers of motorway between Cluj and Zalău.

Frequently Asked Questions

When is the entire Nădășelu–Zimbor section expected to open?

Authorities aim to open traffic on the entire section by late 2026, with unrestricted travel targeted for December 1, 2026.

Who are the main contractors working on this motorway section?

The works are being carried out by UMB for the 25-kilometer stretch and the Ozaltin–Ilgaz–Visio Construct joint venture for the complex viaducts.

What is the financial value of the Nădășelu–Poarta Sălajului project?

The total project value exceeds EUR 861.91 million, supported in part by EUR 239.84 million in European NRRP (PNRR) funds.