Infrastructure projects in Cahul are making significant progress, with the wastewater treatment plant 98% complete, while work on the new headquarters of the “B. P. Hasdeu” Theater continues, according to the MOLDPRES agency. The two objectives, visited by Minister Vladimir Bolea, aim to improve sewerage services and expand access to culture in southern Republic of Moldova.
At the wastewater treatment plant, work was underway on October 13, 2026, on setting up sludge platforms, followed by equipment testing and commissioning preparation. The investment includes the rehabilitation and extension of water supply and sewage networks in Cahul, as well as their construction in the villages of Cotihana and Crihana Veche, benefiting from EUR 54.4 million in financing from the German Government and the European Union, via the KfW development bank. Concurrently, interventions were taking place on the lower level and interior spaces at the new headquarters of the “B. P. Hasdeu” Theater, following the completion of the facade above ground level and testing of electrical and heating systems. The theater project, with a value of EUR 2.59 million allocated through the National Fund for Regional and Local Development and the Ministry of Culture, is set to provide a 250-seat auditorium for over 65,000 residents and visitors.
Frequently Asked Questions
What is the total value of the infrastructure investments in Cahul?
The total value exceeds EUR 57 million, including EUR 54.4 million for water and sanitation and EUR 2.59 million for the new theater.
Who is financing the wastewater treatment and sewage project in Cahul?
The project is funded by the European Union and the German Government through the KfW development bank.
What is the completion status of the wastewater treatment plant?
The wastewater treatment plant has reached a 98% completion rate, with final testing and commissioning preparations underway.