Hotel Olimpic within the Poiana Brașov National Sports Complex was set to undergo repair and renovation works, following the award of a contract valued at approximately EUR 220.66k (RON 1,177,684.95 excluding VAT). The public tender, which received four bids, was won by the company DALYOS FLY SRL from Bistrița, according to public procurement data. The project had a completion deadline of at most 60 days, preparing the accommodation facility for the winter season and for the European Youth Olympic Festival (EYOF), scheduled between February 14 and 21, 2027.
The contracted interventions did not target a reconstruction or full structural overhaul, but rather the modernization of interior finishes, the polycarbonate roof, and specific utility installations. The works entailed surface refinishing with skimming and washable paint, door replacements, and installing LVT flooring after pouring self-leveling screeds. Additionally, the project provided for the replacement of electrical outlets, lighting fixtures with LED wall sconces, partial overhaul of telephony networks, and upgrades to sanitary fittings in the bathrooms. The contractor offered a 36-month warranty for execution and 24 months for equipment. Classified as a two-star facility, Hotel Olimpic features 48 double rooms, three suites, a 120-seat restaurant, and a 50-seat conference room, being part of a larger sports complex that includes Hotel Caraiman, the Ruia Multipurpose Hall, a stadium, an ice rink, and medical recovery facilities.
Frequently Asked Questions
What is the value and completion timeline of the project?
The contract is valued at approximately EUR 220.66k (RON 1,177,684.95 excluding VAT) with an execution deadline of up to 60 days.
Who is performing the work and what upgrades are included?
The contract was awarded to DALYOS FLY SRL from Bistrița, covering interior finishing updates, polycarbonate roof work, LVT flooring installation, LED lighting, and bathroom sanitary replacements.
Why is Hotel Olimpic undergoing this renovation?
The upgrade prepares the two-star hotel for the cold season and for hosting the European Youth Olympic Festival (EYOF) in February 2027.